120 kWpPhoto coming soon
Industrial
Manufacturing hall, Timiș
Timișoara, Timiș County
120 kWp on a membrane roof, sized to the daytime consumption profile.
- Capacity
- 120 kWp
- Annual production
- 138.000 kWh
- CO₂ avoided / year
- 59 t
- Panels
- 270 × 445W monocristalin
- Inverter
- 3 × 40 kW trifazat
- Year
- 2023
- Location
- Timișoara, Timiș County
The challenge
High industrial consumption at peak hours and rising energy costs.
The solution
Three-phase on-grid system with per-string monitoring, integrated into the existing switchboard.
The result
Covers ~65% of annual consumption, with an estimated payback under 5 years.